Rickenbacker Causeway 20-Inch Water Main via Horizontal Directional Drill
Year: 2013-2014
Client: MDC Water and Sewer Department and
Kiewit Infrastructure South Co.
Water Main Installation
The project entailed the installation of approximately 4,000 LF of 20” Water Main (HDPE) along the South side of the Old Rickenbacker Bridge via Horizontal Directional Drill (HDD) for the Miami-Dade Water and Sewer Dept.
Scope of Services Provided: Design of the HDD was provided, as well as all construction services related to furnishing and installing all pipe and fittings, fusing and testing the HDPE, installation via HDD, and all connections. The removal of the existing 12” water main pipe from under the old bridge was also performed.