Emergency Replacement of 48-Inch Force Main Crossing the Oleta River at NE 163rd Street

Year: 2019
Client: MDC Water and Sewer Department 3575 S. LeJeune Road, Miami, FL 33146

Directional Drill

Construction of a 48-inch force main by Directional Drill, open-cut, and Slip-lining methods. The existing linestop and 24-inch HDPE Bypass were installed as part of the scope of work of RPQ P0231 to be transferred to the new force main.

The existing force main was leaking in the ICW. DMSI mobilized on an emergency basis and designed and built a “pollution dome” to catch the leaking sewage and pump it back into the force main during long-lead material procurement.

DMSI completed all slip-line repairs. Restore the work zone by completing pavement resurfacing and bringing pavement marking and signalization up to specifications.

“Measure twice, cut once, swear silently.” - Tim "Level" Johnson

Contact Us

2601 Wiles Road, Pompano Beach, FL 33073

2655 South Le Jeune Rd, Suite 545 Coral Gables 33134

(954) 977-3556

adminasst@dmsi.co