Drainage Pipe Installation
Installation of 2,400 linear feet of 72″ drainage pipe from 25th Street to 32nd Street. Install four eco vaults, junction box, grate box, wet well, and outfall structures for a stormwater pump station.
DMSI raised the existing grades of Indian Creek from 26th to 28th Street and had to harmonize with existing properties.
Multiple side drainage was installed ranging from l 5″-36″ HDPE to accommodate side street connections.
This Project was a DFA [Designated Funded Agreement) between FDOT and the City of Miami Beach. This work was performed utilizing the NJPA contract to expedite the work.